Setting up a watermark cell – BHP


  1. Import the approved company logo (if applicable) and watermark cells into your (by default) C:\BHPBIO CAD Build v8.2\BHPBIO Shared Resources\cell\Project Cells.cel library.
  2. Open the file C:\BHPBIO CADBuild v8.2\BHPBIO Shared Resources\cell\Project Cells.cel in Microstation and go to the Models dialog.
    Click the Import Models button and import the approved cells into your cell library.
  3. Open the CADconform User Manager. Select the default BHPBIO user.
  4. Go to the Certifying tab and set the watermark up as in the screenshot. The Cell Library should be C:\BHPBIO CAD Build v8.2\BHPBIO Shared Resources\cell\Project Cells.cel
    The Marker Cell should be T‐BHP MARKER and the Certification Cell should be your approved company watermark cell.
  5. Click Save and it will exit the User Manager, now you’ll just need to log in as the default user and you should have the new watermark cell.